Material expiry before next planned consumption
RM-10482 · Citric Acid Ingredient · Atlanta Concentrate Plant · detected Sep 02 · 09:03
- Quantity affected
- 18,400 KG
- Time to impact
- 6 days to expiry
- Business impact
- $284K exposure
- Waiting on
- Marcus Chen · Production Planning
Current response
Risk case MR-2026-09182
- Recommended action
- APRA · Alternate Production Run Allocation
- Selected action
- APRA · move PO-88172 to Sep 08
- Expected recovery
- $221K
- Awaiting
- Production feasibility confirmation
Last section: Reviewing APRA impact. Production review required before the run can move.
Why this signal was generated
Condition and threshold behind this signal
- Rule
- Remaining shelf life is shorter than the time to the next planned consumption
- Observed
- Batch expires Sep 08 · next consuming run is Sep 12
- Threshold
- Any gap greater than 0 days on a raw material above $100K raises a critical signal
Source data
Enterprise records this signal was built from
SAP S/4HANA · MM
Batch quantity
18,400 KG
Refreshed 2 min ago
SAP EWM
Available inventory
18,400 KG
Refreshed 2 min ago
SAP PP / PP-PI
Next consumption
Sep 12 · PO-88172
Refreshed 7 min ago
Material Master
Expiry date
Sep 08, 2026
Refreshed 34 min ago
Finance
Inventory value
$284K
Refreshed 18 min ago
Material and batch
- Material
- RM-10482 · Citric Acid Ingredient
- Material type
- Raw material
- Plant
- Atlanta Concentrate Plant
- Quantity
- 18,400 KG
Impact
Production and customer impact
- Orders affected
- PO-88172 · PO-88199 · PO-88224
- Gap to next run
- 4 days after expiry
- Line
- Line 3 · Atlanta
- Customer impact
- None if the run moves to Sep 08
Ownership
Signal anatomy
Source data, condition and threshold behind this signal
Source data
Current date
Sep 02
Expiry
Sep 08
Next planned use
Sep 12
Gap
4 days after expiry
Condition
Planned consumption occurs after expiry
Rule: Remaining shelf life < time to next planned consumption
Risk signal · CRITICAL
Critical material expiry risk
Case history
- 09:03Signal detected from inventory, plan and material master records
- 09:05Priya Nair notified in Teams and email
- 09:14Risk brief prepared · 18,400 KG · $284K exposure
- 09:41Recovery options assessed · APRA recommended
- 10:02Production review sent to Marcus Chen
- 10:11Marcus Chen confirmed production feasibility