All signalsResume Comparing expedite options
HIGHReady for DecisionShortage signal · SIG-4468
Projected shortage before next inbound delivery
RM-22104 · Sweetener Blend · Atlanta Concentrate Plant · detected Sep 02 · 07:41
- Quantity affected
- 14,200 KG short
- Time to impact
- 19 hrs to production impact
- Business impact
- $412K exposure
- Waiting on
- No one · yours to move
OwnerDiego Alvarez
Current response
Risk case MR-2026-09174
- Recommended action
- Expedited supplier delivery
- Alternative
- Partial run with reduced batch size
- Expected recovery
- $318K
- Awaiting
- Nothing · ready for decision
Last section: Comparing expedite options. Two recovery options assessed and ready to decide.
Why this signal was generated
Condition and threshold behind this signal
- Rule
- Projected inventory falls below planned consumption before the next inbound delivery
- Observed
- 14,200 KG short on Sep 05 · next delivery Sep 16
- Threshold
- Any projected shortage inside the frozen production window raises a high signal
Source data
Enterprise records this signal was built from
SAP S/4HANA · MM
Projected stock
8,300 KG
Refreshed 4 min ago
SAP PP / PP-PI
Planned consumption
22,500 KG
Refreshed 9 min ago
Supplier portal
Confirmed delivery
Sep 16
Refreshed 12 min ago
Finance
Exposure
$412K
Refreshed 20 min ago
Material and batch
- Material
- RM-22104 · Sweetener Blend
- Material type
- Raw material
- Plant
- Atlanta Concentrate Plant
- Quantity
- 14,200 KG short
Impact
Production and customer impact
- Orders affected
- PO-88240 · PO-88266
- Time to impact
- 19 hrs
- Line
- Line 1 · Atlanta
- Customer impact
- Consolidated fill rate at risk
Ownership
Diego AlvarezCase ownerOwns the decision and the outcome
Signal anatomy
1 · Source data
4 enterprise records
2 · Condition
14,200 KG short on Sep 05 · next delivery Sep 16
3 · Threshold
Any projected shortage inside the frozen production window raises a high signal
4 · Signal
HIGH · Shortage
Case history
- 07:41Signal detected from projected stock and planned consumption
- 07:52Diego Alvarez notified
- 08:30Expedite request sent to ChemCo Ingredients
- 10:44Supplier confirmed an expedited slot for Sep 05